Operation |
Sets the name of the custom operation. |
Selection Type |
Select one of the following:
Part
|
Applies the operation cost per part. For example, serial number entry is applied per part.
|
Weight
|
Applies the operation cost per unit weight. For example, shipping cost is applied per unit weight.
|
Face
|
Applies the operation cost per square area of the selected faces. For example, painting cost is applied per square area.
|
Edge
|
Applies the operation cost per unit length of the selected edges. For example, deburring is applied per unit length.
|
Stroke
|
Applies the operation cost per stroke operation. For example, a punch cost is applied per stroke.
|
Volume
|
Applies the operation cost per unit volume of the total calculated volume.
|
|
Cost |
Sets the cost value associated with the operation. |
Units |
Displays Cost / Selection Type. |
Setup Cost |
Sets a setup cost per lot for the operation. When the
Operation is used during
the Costing calculation, this Setup
Cost is added to the Setup
folder in the
CostingManager and it is divided by the lot size to get the setup
cost per part. |
Setup Distribution |
Sets how to distribute the Setup Cost:
Divided Over Total Quantity
|
Setup cost is divided by the total number of parts (Setup cost per part = Setup cost / Total number of parts). For example, if the setup cost is 100 and the total number of parts is 100, then the setup cost per part is 1.
|
Divided Over Lot Size
|
Setup cost is divided by the lot size (Setup cost per part = Setup cost / Lot size). For example, if the setup cost is 100 and the lot size is 10, then the setup cost per part is 10.
|
Applied Once Per Part
|
Setup cost is applied per part
(Setup cost per part = Setup cost). For example, if the setup cost is 100 then the setup cost per part is 100.
|
|
Material Class |
Sets the Material Class for
the defined operation:
All
|
All existing material classes are included for the
operation.
|
Selected
|
Only the selected material classes are included.
|
|
Always Include |
Determines if the Setup Cost should be included in the Costing estimates automatically or manually:
Yes
|
The Setup Cost is always included in the
overall cost and appears in the Setup
folder in the CostingManager.
|
No
|
The Setup Cost is not included in the overall cost. To add the Setup Cost to the overall cost, in the CostingManager, right-click the Setup folder and click Select Setup Cost, then click the setup cost.
|
|